The new works will have an investment of EUR 239,284.11 and serve "to improve the sewer and pumping wastewater into the town."
This is 2 pumping stations that are under construction in the municipality, Moncada area and another in the Old Road that is already in the final.
The Municipality of Puerto Lumbreras, in collaboration with the Autonomous Region, has started construction of a pumping station sewage near Puerto Lumbreras Moncada.
This morning, the mayor of Puerto Lumbreras, Maria Angeles Tunisia councilor districts, José María Parra, and Councilman Works, Eliseo Sanchez, visited the site of the new pumping station with which "continue to upgrade networks sanitation and sewerage in the whole town. "
So with this are two pumping stations that are under construction in the municipality, Moncada area and another in the Old Road that is already in the final.
So, the mayor of Puerto Lumbreras, Maria Angeles Tunisia, explained that "these works contribute to improving the conditions and operation of the sewer and water treatment."
Thus, the well pump that has started to be built like the one being built in the Old Way, rectangular in plan, with free ground inside dimensions of 3.50 x 3.10 meters and height 4, 70 meters.
In this well a PVC pipe 300 mm in diameter, where the float level to control and maneuver the sewage pumps are placed are placed.
Furthermore, the two outlet pipes through a 'piece pants' converge in a single drive.
Subsequently driving starts drive through a pipe 250 mm in diameter.
The total length of the discharge pipe is of 632.25 meters, and be high-density polyethylene (PE-100) of 250 mm in diameter, with a nominal pressure of 10 atmospheres.
Thus, the works have an investment of EUR 239,284.11 through the Ministry of Agriculture and Water.
Thus, the actions have included the improvement of the sewerage network, and the construction of a pumping station to the wastewater treatment plant for reuse in irrigation work.
Source: Ayuntamiento de Puerto Lumbreras